SendTech Times
News
INFRASTRUCTURE CONSTRAINT:

Texas Approves $13.8 Billion 765 kV Grid Plan For AI Data Centre Loads

Newsroom brief

AI data centre customers, final routes or ratepayer cost terms remain outside the public record.

Verified against source materialEdited by SendTech Times Cloud & Infrastructure DeskSource: Data Center Knowledge
Texas Approves $13.8 Billion 765 kV Grid Plan For AI Data Centre Loads
Image source: Data Center Knowledge

Texas regulators approved a roughly $13.8 billion transmission strategy that will give ERCOT’s Permian Basin more capacity for large power users, including data centres, before those projects are built.

The Public Utility Commission of Texas unanimously selected a 765-kilovolt network in April 2025, choosing a more flexible design over a cheaper 345 kV alternative estimated at $12.95 billion.

The decision followed a sharp change in the region’s demand outlook.

ERCOT’s earlier planning focused on replacing onsite generation as Permian Basin oil operations electrified.

By 2024, transmission providers were forecasting an “exponential increase” in non-oil-and-gas demand, led by cryptocurrency mining, data centres and hydrogen electrolysis.

Those projects represented 11.6 GW of projected demand by 2030, nearly matching the oil-and-gas load that had originally justified the Permian reliability initiative.

Combined demand was forecast at 23 GW by 2030 and 26.4 GW by 2038.

The speed of that growth became as important as its size.

ERCOT’s staff memo said large loads can be added to the system in as little as 6 to 12 months, creating a risk that actual Permian demand could exceed today’s 2038 forecast.

Rather than continue adding 345 kV lines around a fixed projection, ERCOT evaluated whether extra-high-voltage infrastructure could handle demand that may emerge in different places and on a faster schedule.

Why ERCOT chose 765 kV

After workshops, technical studies and stakeholder meetings, PUCT staff recommended the 765 kV option for the Permian Basin Reliability Plan.

ERCOT estimated the full 2038 plan at $13.8 billion with that design.

A 500 kV alternative was projected to cost $15.32 billion.

The commission concluded that the 765 kV architecture justified its premium over the 345 kV plan because it offered greater transfer capability and more room to accommodate uncertain future demand.

Staff also described the project as a foundation for a “looped, networked statewide plan.”

Commissioner Kathleen Jackson said the Permian Basin had “outgrown its infrastructure.” Although the 765 kV option required a higher initial investment, she said it provided “more transfer capability” and longer-term benefits if demand continued to rise.

More capacity, fewer corridors

ERCOT found that the 765 kV network would provide 600 MW to 3,000 MW more regional transfer capability than the comparable 345 kV alternative.

It would also reduce annual transmission losses by about 5%, require fewer transmission corridors and expand siting options for generation resources and large electrical loads.

For hyperscale developers, the practical benefit is not simply larger lines.

More substations could support campuses requiring hundreds of megawatts, easing congestion and giving projects more potential locations to connect to the grid.

Neil Osnato, founder of Persistence Analytics Group, told Data Center Knowledge that AI demand is “larger, faster-moving, less geographically fixed, and more sensitive to power availability” than many traditional forms of economic development.

Higher-capacity transmission, he said, allows utilities to absorb uncertainty over where data centres, hydrogen production, oil-and-gas electrification and other large loads ultimately emerge.

“Texas is not just planning for more electricity.

It is planning for uncertainty,” Osnato said.

A statewide planning bet

The strategy builds on Texas’ earlier Competitive Renewable Energy Zones transmission project.

CREZ was designed to move West Texas wind generation, but its high-capacity corridors and substations later helped attract hyperscale data centre development.

ERCOT’s 2024 Regional Transmission Plan points toward a broader version of that approach.

A statewide 765 kV network would provide greater transfer capability, reduce congestion and transmission losses, and expand siting options for generation and large electrical loads.

Major parts of both the 345 kV and 765 kV plans would still be needed even if forecast load growth falls roughly 20 GW below current expectations.

The approved Permian plan therefore places transmission investment ahead of precise knowledge about which major power users will connect or where they will locate.

Texas’ previous grid buildout helped determine where new demand could grow; the 765 kV decision extends that model to an era in which the demand itself is arriving faster and with less geographic certainty.

Share this article
inXf

Related articles

More
Texas Grid Rules Push AI Data Centres To Pay Interconnection Costs
Cloud & Data Centers

Texas Grid Rules Push AI Data Centres To Pay Interconnection Costs

Texas regulators are moving AI data-centre projects into a stricter grid-planning process that adds financial security, interconnection charges and curtailment disclosure.

Texas AI Campus Filing Names 525.5 MW Behind One Wind Interconnection
Cloud & Data Centers

Texas AI Campus Filing Names 525.5 MW Behind One Wind Interconnection

Texas regulators are considering whether Crusoe and Ensign Infrastructure must curtail a second AI data-centre load behind the Goodnight 1 wind farm during grid emergencies. Data Center Knowledge reported that the combined behind-the-meter load would reach 525.5 MW under the Senate Bill 6 review.

Texas Grid Rules Put 75MW Data Center Loads Into A New ERCOT Queue
Cloud & Data Centers

Texas Grid Rules Put 75MW Data Center Loads Into A New ERCOT Queue

Texas regulators approved ERCOT’s new connection process for large-load projects of 75MW or more, forcing data centers into a grid study before capacity is allocated.

Texas Grid Audit Freezes Data Centre Queue As AI Demand Builds
Cloud & Data Centers

Texas Grid Audit Freezes Data Centre Queue As AI Demand Builds

Capacity reported that Texas has paused new data centre approvals while ERCOT and PUCT audit Batch Zero projects seeking grid access, a group of 250 to 300 projects representing about 200GW of future demand.

Meta Plans $9.17bn Alberta Data Centre With 1GW Power Target
Cloud & Data Centers

Meta Plans $9.17bn Alberta Data Centre With 1GW Power Target

A 1GW Meta data-centre plan in Sturgeon County carries CA$13 billion in expected investment, a Project Greenlight power component and no public first-service or grid-approval timetable.

Galaxy’s 74 MW McGregor AI Campus Commits To Private Texas Substation
Cloud & Data Centers

Galaxy’s 74 MW McGregor AI Campus Commits To Private Texas Substation

Galaxy Digital plans a 500-acre AI and high-performance computing campus in McGregor, Texas, with a 74 MW first phase and project commitments covering a private substation, utility assurances and water infrastructure.

White House Presses PJM Grid Reform As AI Power Demand Rises
Cloud & Data Centers

White House Presses PJM Grid Reform As AI Power Demand Rises

The White House warned PJM Interconnection to reform its board governance and stakeholder process as AI data centres and other large loads intensify disputes over grid reliability, electricity prices and infrastructure cost allocation.

Amazon Grid Proposal Tests Who Pays For AI Data-Centre Lines
Cloud & Data Centers

Amazon Grid Proposal Tests Who Pays For AI Data-Centre Lines

Data Center Knowledge reported that Amazon asked Virginia regulators to let hyperscale data-centre customers voluntarily fund project-specific transmission upgrades, while Dominion argued the issue belongs in a separate proceeding.

Keep Reading

More Stories

Latest
Kepler Targets 2027 Production for HBM Replacement MemoryCloud & Data CentersOct 6, 2026Kepler Targets 2027 Production for HBM Replacement MemoryEE Times reports that Kepler Computing is preparing 3D ferroelectric memory for 2027 production, promising higher capacity and bandwidth per watt while limiting reliance on advanced-node lithography.Yokogawa Opens Singapore Hub For Industrial Cyber ResilienceCapital & PolicyOct 6, 2026Yokogawa Opens Singapore Hub For Industrial Cyber ResilienceYokogawa Engineering Asia has launched a Singapore center focused on OT cyber resilience, training, response planning and recovery coordination for Southeast Asia, Oceania and Taiwan.ClickFix Attack Uses Browser Cache To Hide Malware PayloadCybersecurityOct 6, 2026ClickFix Attack Uses Browser Cache To Hide Malware PayloadMicrosoft Threat Intelligence traced a ClickFix cache-smuggling method that preloads malware into browser caches, then uses file size checks and a pasted Run command to launch later credential-theft stages.VOA Tests Six-Month Startup Buildout Before Funding DecisionsFintech & Digital PaymentsOct 6, 2026VOA Tests Six-Month Startup Buildout Before Funding DecisionsTechCabal’s interview with VOA Venture Partners founder Victoria Olayide Adesanya describes a six-month build programme that lets the firm work inside African financial-infrastructure startups before deciding whether to invest.Bitcoin Holds $86,000 As Dollar Index Hits 18-Month HighCrypto/Web3Oct 6, 2026Bitcoin Holds $86,000 As Dollar Index Hits 18-Month HighCoinDesk reported that bitcoin stayed near $86,000 while the U.S. Dollar Index reached about 102.5, with U.S. rate expectations and European political risks strengthening the dollar backdrop.Google Freezes OSS Bug Bounty Reports After AI Submission FloodCybersecurityOct 6, 2026Google Freezes OSS Bug Bounty Reports After AI Submission FloodGoogle has stopped accepting new product vulnerability reports in its OSS VRP after invalid automated submissions swamped reviewers, while older reports and some Cloud VRP routes remain open.Fleuret AI Raises €4M For Continuous AI Pentesting PlatformCybersecurityOct 6, 2026Fleuret AI Raises €4M For Continuous AI Pentesting PlatformTech.eu reported that French startup Fleuret AI raised €4 million in pre-seed funding to develop an agentic-AI platform that turns penetration testing into a continuous security process.GFT Analysis Says AI Documentation Can Cut Maintenance Work 30%Fintech & Digital PaymentsOct 6, 2026GFT Analysis Says AI Documentation Can Cut Maintenance Work 30%A GFT Technologies analysis says AI-linked software documentation can cut maintenance effort and speed developer onboarding when knowledge assets stay synchronized with code changes.Schneider Electric Lines Up $22.6 Billion PTC DealAIOct 5, 2026Schneider Electric Lines Up $22.6 Billion PTC DealSchneider Electric plans to buy PTC in a cash transaction valuing the US engineering software provider’s equity at about $22.6 billion, adding product-lifecycle software to its industrial AI push.Aggarwal Pledges Ola Electric Stake To Fund ₹1,000 Cr Rights IssueCapital & PolicyOct 5, 2026Aggarwal Pledges Ola Electric Stake To Fund ₹1,000 Cr Rights IssueOla Electric founder Bhavish Aggarwal pledged 20 Cr shares to finance his participation in a rights issue that forms part of a larger ₹1,500 Cr fundraising plan.Natrona Schools AI Review Puts Student Privacy Ahead Of Classroom Tool UseAIOct 5, 2026Natrona Schools AI Review Puts Student Privacy Ahead Of Classroom Tool UseNatrona County trustees questioned whether teacher AI tools expose student data, even as existing district rules already ban unauthorized generative AI use by students.AMD Prices 256-Core EPYC 9996 At $14,904 For Server BuyersChips & SemiconductorsOct 5, 2026AMD Prices 256-Core EPYC 9996 At $14,904 For Server BuyersTechRadar reports that AMD’s 6th Gen EPYC 9006 “Venice” lineup includes a 256-core EPYC 9996 with 512 threads, 1GB of L3 cache, a 600W default power rating and a $14,904 list price for 1,000-unit orders.