SendTech Times
News
INFRASTRUCTURE CONSTRAINT:

PJM Plan Makes AI Data Centres Prove Capacity For Firm Power

Newsroom brief

Data Center Knowledge reported that PJM is proposing a FERC-filed framework that would make new AI data centres secure generating capacity or face curtailments during grid shortages.

Verified against source materialEdited by SendTech Times Cloud & Infrastructure DeskSource: Data Center Knowledge
PJM Plan Makes AI Data Centres Prove Capacity For Firm Power
Image source: Data Center Knowledge

For AI data centres in PJM, a grid connection may no longer be enough to secure firm power.

A July 27 board-approved framework would separate interconnection from reliable capacity service and send that distinction to the Federal Energy Regulatory Commission, Data Center Knowledge reported.

The proposal separates two steps that hyperscale developers have often treated as linked: getting connected to the grid and receiving reliable capacity service during shortages.

PJM projects roughly 70 GW of new large-load demand by 2038, while about 15 GW of generation has retired since 2022 and two recent capacity auctions cleared below the system reliability requirement.

Firm Service Depends On Capacity Proof

New large-load customers would need to bring enough generating capacity, sign adequate supply arrangements or accept a lower service status when the grid lacks resources.

Neil Osnato of Persistence Analytics Group said PJM is beginning to separate being connected from being firm, with new loads asked to earn the reliability product they once largely assumed.

The operating change would matter most for campuses that can obtain an interconnection position before their power supply plan is complete.

Under the proposed Interim Resource Adequacy Service, large loads that lack sufficient capacity would be curtailed before PJM turns to broader Pre-Emergency Load Management measures during shortage conditions.

June 2027 Framework Adds A Curtailment Track

The IRAS framework would begin June 1, 2027 if regulators approve it.

Customers seeking the same firm-service treatment as existing load would have to add enough new capacity to the system or remain under the interim service until adequate supply is available.

PJM also plans a Large Load Registry for major electricity users.

The registry would improve forecasting and give states better information for retail rate design and cost allocation, because PJM cannot create separate retail rate classes for data centres on its own.

Backstop Procurement Targets 6,831 MW Shortfall

The capacity package includes a one-time Reliability Backstop Procurement starting in September after the 2028-2029 Base Residual Auction produced a 6,831 MW shortfall.

Signed contracts for new supply, approved new generation and committed demand-side participation by large-load sites would reduce the procurement target, limiting the risk that PJM buys capacity already covered by other arrangements.

Demand response resources and distributed energy resources could qualify if developers show participating sites and long-term commitments.

Selected projects would still use the standard PJM interconnection process rather than receiving a special queue position through the backstop procurement.

The cost argument is explicit.

The board said existing consumers should not bear higher capacity costs caused by new large loads that do not bring or contract for the supply needed to serve them.

Rob Gramlich of Grid Strategies told Data Center Knowledge that ERCOT, MISO and SPP are considering similar policies.

The framework would make power procurement part of the project-finance case from the start.

Developers must now show which generation, contracts, storage or flexible-load arrangements can perform during grid stress, while the megawatt test and FERC timetable remain unresolved.

Share this article
inXf

Related articles

More
PJM Plan Makes AI Data Centres Bring Power Or Accept Curtailment
Cloud & Data Centers

PJM Plan Makes AI Data Centres Bring Power Or Accept Curtailment

Data Center Knowledge reported that PJM's proposed IRAS framework would separate grid connection from firm service for new AI-scale loads, pushing data centre developers to bring capacity, contract bilaterally or accept curtailment during shortages.

Grid Operators Seek Delay On FERC Data Centre Power Rules
Cloud & Data Centers

Grid Operators Seek Delay On FERC Data Centre Power Rules

Five of six U.S. grid operators asked FERC for more time on large-load interconnection rules, leaving data centre developers waiting for enforceable power-access tariffs.

PJM Backup-Generator Warnings Test Large-Load Grid Tool
Cloud & Data Centers

PJM Backup-Generator Warnings Test Large-Load Grid Tool

Data Center Knowledge reported that PJM issued emergency backup-generator warnings during a July heat wave but did not dispatch customer-owned generators, leaving total available large-load backup capacity undisclosed.

White House Presses PJM Grid Reform As AI Power Demand Rises
Cloud & Data Centers

White House Presses PJM Grid Reform As AI Power Demand Rises

The White House warned PJM Interconnection to reform its board governance and stakeholder process as AI data centres and other large loads intensify disputes over grid reliability, electricity prices and infrastructure cost allocation.

AI Data Centres Force Utilities To Price Power Queues Before Land Deals
Cloud & Data Centers

AI Data Centres Force Utilities To Price Power Queues Before Land Deals

Utilities and grid-reliability specialists say hyperscale AI campuses are changing how large loads are studied, priced and connected, with FirstEnergy using a two-stage load study and bigger Ohio transmission plans.

AI Rack Density Pushes Data Centres Toward Power and Cooling Limits
Cloud & Data Centers

AI Rack Density Pushes Data Centres Toward Power and Cooling Limits

Data Center Knowledge analysis shows AI rack power moving from typical 11 kW rooms to 100 kW-plus deployments, with cooling, power distribution and grid access setting the ceiling.

Amazon Grid Proposal Tests Who Pays For AI Data-Centre Lines
Cloud & Data Centers

Amazon Grid Proposal Tests Who Pays For AI Data-Centre Lines

Data Center Knowledge reported that Amazon asked Virginia regulators to let hyperscale data-centre customers voluntarily fund project-specific transmission upgrades, while Dominion argued the issue belongs in a separate proceeding.

AI Data Centres Pull Solid-State Transformers Into Commercial Power Plans
Cloud & Data Centers

AI Data Centres Pull Solid-State Transformers Into Commercial Power Plans

Ars Technica reported that AI data centre power demand is accelerating interest in solid-state transformers, which can convert grid AC power into DC power for accelerator racks while easing equipment footprint and supply-chain constraints.

Keep Reading

More Stories

Latest
Kepler Targets 2027 Production for HBM Replacement MemoryCloud & Data CentersOct 6, 2026Kepler Targets 2027 Production for HBM Replacement MemoryEE Times reports that Kepler Computing is preparing 3D ferroelectric memory for 2027 production, promising higher capacity and bandwidth per watt while limiting reliance on advanced-node lithography.Yokogawa Opens Singapore Hub For Industrial Cyber ResilienceCapital & PolicyOct 6, 2026Yokogawa Opens Singapore Hub For Industrial Cyber ResilienceYokogawa Engineering Asia has launched a Singapore center focused on OT cyber resilience, training, response planning and recovery coordination for Southeast Asia, Oceania and Taiwan.ClickFix Attack Uses Browser Cache To Hide Malware PayloadCybersecurityOct 6, 2026ClickFix Attack Uses Browser Cache To Hide Malware PayloadMicrosoft Threat Intelligence traced a ClickFix cache-smuggling method that preloads malware into browser caches, then uses file size checks and a pasted Run command to launch later credential-theft stages.VOA Tests Six-Month Startup Buildout Before Funding DecisionsFintech & Digital PaymentsOct 6, 2026VOA Tests Six-Month Startup Buildout Before Funding DecisionsTechCabal’s interview with VOA Venture Partners founder Victoria Olayide Adesanya describes a six-month build programme that lets the firm work inside African financial-infrastructure startups before deciding whether to invest.Bitcoin Holds $86,000 As Dollar Index Hits 18-Month HighCrypto/Web3Oct 6, 2026Bitcoin Holds $86,000 As Dollar Index Hits 18-Month HighCoinDesk reported that bitcoin stayed near $86,000 while the U.S. Dollar Index reached about 102.5, with U.S. rate expectations and European political risks strengthening the dollar backdrop.Google Freezes OSS Bug Bounty Reports After AI Submission FloodCybersecurityOct 6, 2026Google Freezes OSS Bug Bounty Reports After AI Submission FloodGoogle has stopped accepting new product vulnerability reports in its OSS VRP after invalid automated submissions swamped reviewers, while older reports and some Cloud VRP routes remain open.Fleuret AI Raises €4M For Continuous AI Pentesting PlatformCybersecurityOct 6, 2026Fleuret AI Raises €4M For Continuous AI Pentesting PlatformTech.eu reported that French startup Fleuret AI raised €4 million in pre-seed funding to develop an agentic-AI platform that turns penetration testing into a continuous security process.GFT Analysis Says AI Documentation Can Cut Maintenance Work 30%Fintech & Digital PaymentsOct 6, 2026GFT Analysis Says AI Documentation Can Cut Maintenance Work 30%A GFT Technologies analysis says AI-linked software documentation can cut maintenance effort and speed developer onboarding when knowledge assets stay synchronized with code changes.Schneider Electric Lines Up $22.6 Billion PTC DealAIOct 5, 2026Schneider Electric Lines Up $22.6 Billion PTC DealSchneider Electric plans to buy PTC in a cash transaction valuing the US engineering software provider’s equity at about $22.6 billion, adding product-lifecycle software to its industrial AI push.Aggarwal Pledges Ola Electric Stake To Fund ₹1,000 Cr Rights IssueCapital & PolicyOct 5, 2026Aggarwal Pledges Ola Electric Stake To Fund ₹1,000 Cr Rights IssueOla Electric founder Bhavish Aggarwal pledged 20 Cr shares to finance his participation in a rights issue that forms part of a larger ₹1,500 Cr fundraising plan.Natrona Schools AI Review Puts Student Privacy Ahead Of Classroom Tool UseAIOct 5, 2026Natrona Schools AI Review Puts Student Privacy Ahead Of Classroom Tool UseNatrona County trustees questioned whether teacher AI tools expose student data, even as existing district rules already ban unauthorized generative AI use by students.AMD Prices 256-Core EPYC 9996 At $14,904 For Server BuyersChips & SemiconductorsOct 5, 2026AMD Prices 256-Core EPYC 9996 At $14,904 For Server BuyersTechRadar reports that AMD’s 6th Gen EPYC 9006 “Venice” lineup includes a 256-core EPYC 9996 with 512 threads, 1GB of L3 cache, a 600W default power rating and a $14,904 list price for 1,000-unit orders.