Spain AI Campus Seeks 300 MW With On-Site Power Plan

Newsroom brief

Data Center Knowledge reported that EdgeMode, BlackBerry AIF and Mora are seeking regional support for DC MALPICA, a proposed €3 billion ($3.4 billion), 300 MW AI campus whose power model remains partly undisclosed.

Verified against source materialEdited by SendTech Times Cloud & Infrastructure DeskSource: Data Center Knowledge
Spain AI Campus Seeks 300 MW With On-Site Power Plan
Image source: Data Center Knowledge

A proposed 300 MW AI campus in central Spain is moving through regional permitting with its own power-generation plan, with electricity access central to a Data Center Knowledge project account of the €3 billion ($3.4 billion) data centre proposal rather than a later utility step.

EdgeMode, BlackBerry AIF and the town of Mora presented the DC MALPICA AI project on Monday to officials from the Castilla-La Mancha regional government.

The plan covers two 150,000 square metre AI data centres, and the developers are preparing an application for regional Priority Project status to accelerate permitting for investments considered strategically important.

DC MALPICA Pairs 300 MW Capacity With Local Power

The campus is designed to generate its own electricity and reduce dependence on the conventional grid.

The same project material refers to technologies intended to minimise water consumption.

The power model moves part of the utility question into the site design.

Electricity supply, cooling and interconnection sit alongside the buildings in the project plan before the regional approval process is complete.

Bloom Energy’s Europe director, Reto Zueger, attended the presentation with executives from EdgeMode, BlackBerry AIF and other partners.

The project account did not assign Bloom Energy a role, and a company spokesperson declined to comment.

Dell'Oro Analyst Names Grid Interconnection As The Constraint

Alex Cordovil, research director at Dell'Oro Group, told Data Center Knowledge that grid interconnection has become the main determinant of whether an AI campus reaches operation.

His comments framed on-site generation as a strategic asset, not a backup plan, for developers trying to keep projects moving if grid service is delayed.

The analyst used Nscale’s AI campus in Norway as the comparison point after a delayed grid connection pushed that developer toward an on-site fuel cell solution.

The Spain proposal follows the same infrastructure logic: dedicated generation can support construction sequencing while preserving room for future expansion if utility capacity arrives later.

Cordovil placed the Spanish campus among the largest AI campuses currently planned outside France.

He compared the proposed 300 MW scale with most announced European AI campuses, which he put between roughly 50 MW and 300 MW, while France has several announced gigawatt-scale AI projects.

Regional Approval Still Defines The Timeline

Officials from Castilla-La Mancha ministries responsible for economic development, energy transition and telecommunications attended the Monday presentation.

Priority Project designation is meant to speed permitting, but the project still has to move through the regional approval process before construction can proceed at scale.

Developers estimate the investment at €3 billion ($3.4 billion).

Their employment forecast covers up to 5,000 construction jobs and roughly 1,000 permanent direct and indirect positions after the campus enters service.

BlackBerry AIF CEO José Mora said artificial intelligence needs a new generation of infrastructure and that Spain has an opportunity to become one of Europe’s major technology hubs.

DC MALPICA was presented as a project that combines AI computing capacity with energy independence and sustainability.

The available project record leaves the central infrastructure proof unresolved: DC MALPICA still has to show how much of its planned 300 MW load will come from on-site generation, what fuel will supply it and how the campus will connect to Spain’s electric grid.

Share this article
inXf

Related articles

More
PJM Plan Makes AI Data Centres Prove Capacity For Firm Power
Cloud & Data Centers

PJM Plan Makes AI Data Centres Prove Capacity For Firm Power

Data Center Knowledge reported that PJM is proposing a FERC-filed framework that would make new AI data centres secure generating capacity or face curtailments during grid shortages.

Georgia Power Filings Show 3.2GW Grid Queue Before OpenAI Camellia Debut
Cloud & Data Centers

Georgia Power Filings Show 3.2GW Grid Queue Before OpenAI Camellia Debut

Data Center Knowledge reviewed PSC filings that recorded a 3,200MW customer commitment and an anonymised 3,210MW project before OpenAI unveiled its $20 billion Project Camellia AI campus.

Meta Says Hyperion AI Campus Will Reach 5 GW In Louisiana
Cloud & Data Centers

Meta Says Hyperion AI Campus Will Reach 5 GW In Louisiana

Data Center Knowledge reported that Meta's Hyperion AI campus in Louisiana is being expanded to 5 GW and more than $50 billion of investment, with Entergy filings listing 1,500 MW of new solar and hybrid resources and customer-funded transmission for the expansion.

PJM Backup-Generator Warnings Test Large-Load Grid Tool
Cloud & Data Centers

PJM Backup-Generator Warnings Test Large-Load Grid Tool

Data Center Knowledge reported that PJM issued emergency backup-generator warnings during a July heat wave but did not dispatch customer-owned generators, leaving total available large-load backup capacity undisclosed.

Finland Data Centre Growth Faces Grid And Heat-Reuse Tests
Cloud & Data Centers

Finland Data Centre Growth Faces Grid And Heat-Reuse Tests

Finland is attracting AI data centre projects because of low-carbon power, cool weather and land, Data Center Knowledge reported, but grid connections, permitting and waste-heat rules now determine how much capacity becomes operational.

Galaxy’s 74 MW McGregor AI Campus Commits To Private Texas Substation
Cloud & Data Centers

Galaxy’s 74 MW McGregor AI Campus Commits To Private Texas Substation

Galaxy Digital plans a 500-acre AI and high-performance computing campus in McGregor, Texas, with a 74 MW first phase and project commitments covering a private substation, utility assurances and water infrastructure.

Amazon Grid Proposal Tests Who Pays For AI Data-Centre Lines
Cloud & Data Centers

Amazon Grid Proposal Tests Who Pays For AI Data-Centre Lines

Data Center Knowledge reported that Amazon asked Virginia regulators to let hyperscale data-centre customers voluntarily fund project-specific transmission upgrades, while Dominion argued the issue belongs in a separate proceeding.

Nebius Sets October 2027 First Phase For 1.2GW Pennsylvania AI Campus
Cloud & Data Centers

Nebius Sets October 2027 First Phase For 1.2GW Pennsylvania AI Campus

Data Center Dynamics identified a 260MW first phase for Nebius’ planned Pennsylvania AI cloud campus, with full buildout at 1.2GW and a dedicated PPL Electric Utilities energy-service agreement.

Keep Reading

More Stories

Latest
Hugging Face Hack Pushes AI Agents Into Cybersecurity SpotlightAIAug 8, 2026Hugging Face Hack Pushes AI Agents Into Cybersecurity SpotlightCNBC reported that Black Hat cybersecurity leaders treated the Hugging Face AI-agent breach as a turning point for governing autonomous cyber models rather than a one-off failure.Alibaba Tests Revenue Sharing For Commercial Qwen AI UseAIAug 8, 2026Alibaba Tests Revenue Sharing For Commercial Qwen AI UseAI News reported that Alibaba plans revenue-sharing terms for some commercial users of its next Qwen open-weight AI model, following a licensing pattern already used by Moonshot for Kimi K3.Meta Ordered To Fund $567M New Mexico Youth Mental Health PlanCapital & PolicyAug 8, 2026Meta Ordered To Fund $567M New Mexico Youth Mental Health PlanArs Technica reported that a New Mexico judge ordered Meta to provide $567 million for treatment, screening, awareness and prevention after finding that its platforms contributed to a public nuisance.Harvey Funding Talks Could Lift Legal AI Startup To $15.5B ValuationAIAug 8, 2026Harvey Funding Talks Could Lift Legal AI Startup To $15.5B ValuationSiliconANGLE reported that Harvey AI is seeking at least $500 million in new funding that could value the legal AI startup at $15.5 billion after annualized revenue passed $350 million.Vietnam Shows Shopee-TikTok Shop Race Tightening In Southeast AsiaScience & TechAug 7, 2026Vietnam Shows Shopee-TikTok Shop Race Tightening In Southeast AsiaTech Collective SEA wrote that Shopee’s Vietnam share fell from 61% to 53% between May 2025 and April 2026 as TikTok Shop rose from 33% to 44%, showing how social commerce is reshaping regional ecommerce infrastructure.China Opens Security Review Of Palo Alto Networks ProductsCybersecurityAug 7, 2026China Opens Security Review Of Palo Alto Networks ProductsChina's cyberspace regulator opened a security review of Palo Alto Networks products, with no named product line, technical flaw or decision timetable disclosed.AI Pioneers Split Over Risk As Compute Buildout AcceleratesAIAug 7, 2026AI Pioneers Split Over Risk As Compute Buildout AcceleratesData Center Knowledge reported that Geoffrey Hinton, Fei-Fei Li and Andrew Ng disagreed at Ai4 over AI risk, jobs, openness and regulation, leaving infrastructure investors to plan capacity amid unsettled deployment rules.SpaceX Asks FCC To Wind Down $4.5bn Rural Broadband SupportTelco & ConnectivityAug 7, 2026SpaceX Asks FCC To Wind Down $4.5bn Rural Broadband SupportLight Reading reported that SpaceX urged the FCC to sunset High-Cost rural broadband subsidies, while rural telecom and electric-cooperative groups said LEO satellite coverage cannot replace terrestrial network support.OpenAI Expands Free ChatGPT Access In GPT-5.6 RolloutAIAug 7, 2026OpenAI Expands Free ChatGPT Access In GPT-5.6 RolloutBleepingComputer reported that OpenAI is rolling out GPT-5.6 Sol for paid ChatGPT users and GPT-5.6 Luna for Free and Go users, pairing unlimited free text chats with a new reasoning control and additional safeguards for users believed to be under 18.JLL Data Centre Report Shows Middle East Pipeline Pause As FLAPD GrowsCapital & PolicyAug 7, 2026JLL Data Centre Report Shows Middle East Pipeline Pause As FLAPD GrowsData Center Dynamics reported that JLL's EMEA Mid-Year Data Centre Report 2026 put FLAPD live capacity at 3.8GW, while the Middle East had 2.6GW in development paused and 13.8GW in planning.AWS Adds Persistent Runtime Instances For Production AI AgentsCloud & Data CentersAug 7, 2026AWS Adds Persistent Runtime Instances For Production AI AgentsAWS announced runtime instances for Amazon Bedrock AgentCore Runtime, adding managed infrastructure for multi-agent workflows, shared sessions lasting up to 14 days and GPU-supported production agent deployments.AI Patch Study Keeps Humans In Vulnerability ReviewsCybersecurityAug 7, 2026AI Patch Study Keeps Humans In Vulnerability ReviewsThe Register reported that 1Password Off-by-1 Labs tested 6,080 AI-generated patches across six CVEs and found clean autonomous fixes in 26.0 percent of cases, leaving security teams with a supervision problem rather than a replacement for vulnerability review.