News
CAPACITY TEST:

Georgia Power Filings Show 3.2GW Grid Queue Before OpenAI Camellia Debut

Newsroom brief

Data Center Knowledge reviewed PSC filings that recorded a 3,200MW customer commitment and an anonymised 3,210MW project before OpenAI unveiled its $20 billion Project Camellia AI campus.

Verified against source materialEdited by SendTech Times Cloud & Infrastructure DeskSource: Data Center Knowledge
Georgia Power Filings Show 3.2GW Grid Queue Before OpenAI Camellia Debut
Image source: Data Center Knowledge

A 3.2GW AI campus was moving through Georgia utility planning before OpenAI gave the project a public name.

Data Center Knowledge reviewed Georgia Public Service Commission filings that recorded a 3,200MW customer commitment and an anonymized 3,210MW project before OpenAI unveiled the $20 billion Project Camellia campus.

The PSC record establishes the load sequence before the public launch, but it does not identify the confidential customer.

Project Camellia was announced as a 3.2GW AI campus, and the filing material shows how large-load planning can begin months before communities, developers, and other power users see the named project.

PSC Filings Recorded A 3,200MW Commitment

In a first-quarter 2026 large-load filing, Georgia Power recorded 3,200MW of new customer commitments for April 2026 and placed the fuller update in the next quarterly cycle.

OpenAI gave Project Camellia its public name three months after that April commitment appeared in the utility record.

An accompanying planning attachment identifies an anonymized project in technical review with an announced load of 3,210MW, an initial in-service date of Q2 2028, and a ramp to approximately 3.2GW by 2031.

The timeline broadly matches OpenAI's plan to energize the campus in phases beginning in 2028.

Neil Osnato, founder of Persistence Analytics Group, noted that the proposed 3.2GW draw was exceptional for utility planning.

His assessment treated the campus as a system-level load, not a conventional customer connection.

Georgia Power Raised Its Load Forecast

Georgia Power's January 2025 Integrated Resource Plan provides the planning context for early confidential evaluations.

The filing describes ongoing utility talks with large power users and incorporates both prospective and committed projects into long-term demand modeling.

The utility raised its load-growth forecast to 8,200MW through the winter of 2030-31, exceeding the 2023 IRP update by more than 2,200MW, and projected nearly 6,000MW of new demand by the winter of 2028-29.

The filing also proposed new generation resources and strategic transmission investments.

Whether Project Camellia contributed to that forecast cannot be determined from the public record.

A single 3.2GW campus illustrates the size of customer requests that can alter a utility's planning horizon before the project enters local economic-development debate and before local documents name the buyer.

OpenAI Deal Includes Demand Response Terms

Georgia Power's OpenAI agreement carried terms that were not visible in the PSC filings.

The utility put OpenAI under responsibility for full infrastructure and electric-service costs, financial assurances designed to protect existing customers and a 25-year agreement that includes up to 1,000MW of flexible demand response.

Under that arrangement, peak-demand periods can trigger reductions in power delivered to the campus.

The utility described the clause as one of the largest demand-response commitments attached to a single facility in the United States, making curtailment a formal part of the campus's grid connection rather than an afterthought.

Discovery responses in the PSC docket also illustrate how Georgia Power weighs large-load evidence.

Executed electric-service contracts carry more weight in forecasts than service requests, and one proposed data-center project left the queue after the developer stopped responding, lacked an operator, and no longer marketed the site as a data-center location.

Georgia Power's March 31 large-load materials reported committed large-load customers at 12.4GW, the economic-development pipeline at 76.2GW, and committed projects at 31, most of them data centres.

Those figures place Project Camellia within a much larger queue of AI and hyperscale power requests across the utility system.

Public Records Stop Before Customer Confirmation

County-level records add another boundary around the timeline.

The Effingham County Board of Commissioners had no Project Camellia references in agendas, meeting packets, or minutes before the announcement, and its open-records response found no maintained development, incentive, or correspondence files matching the request.

OpenAI has pledged to share Project Camellia water-use data, publish annual independent audits, and maintain community communication.

That transparency commitment begins after the named campus enters public view; the PSC timeline captures the earlier layer where large-load planning can appear under confidential customer labels.

The PSC filings therefore document the load size, stage, and energization schedule without naming the customer.

The PSC records do not identify OpenAI as the anonymous customer or establish when the 3.2GW load became commercially certain.

Share this article
inXf

Related articles

More
Meta Says Hyperion AI Campus Will Reach 5 GW In Louisiana
Cloud & Data Centers

Meta Says Hyperion AI Campus Will Reach 5 GW In Louisiana

Data Center Knowledge reported that Meta's Hyperion AI campus in Louisiana is being expanded to 5 GW and more than $50 billion of investment, with Entergy filings listing 1,500 MW of new solar and hybrid resources and customer-funded transmission for the expansion.

Amazon Grid Proposal Tests Who Pays For AI Data-Centre Lines
Cloud & Data Centers

Amazon Grid Proposal Tests Who Pays For AI Data-Centre Lines

Data Center Knowledge reported that Amazon asked Virginia regulators to let hyperscale data-centre customers voluntarily fund project-specific transmission upgrades, while Dominion argued the issue belongs in a separate proceeding.

Spain AI Campus Seeks 300 MW With On-Site Power Plan
Cloud & Data Centers

Spain AI Campus Seeks 300 MW With On-Site Power Plan

Data Center Knowledge reported that EdgeMode, BlackBerry AIF and Mora are seeking regional support for DC MALPICA, a proposed €3 billion ($3.4 billion), 300 MW AI campus whose power model remains partly undisclosed.

Galaxy’s 74 MW McGregor AI Campus Commits To Private Texas Substation
Cloud & Data Centers

Galaxy’s 74 MW McGregor AI Campus Commits To Private Texas Substation

Galaxy Digital plans a 500-acre AI and high-performance computing campus in McGregor, Texas, with a 74 MW first phase and project commitments covering a private substation, utility assurances and water infrastructure.

Texas Grid Rules Push AI Data Centres To Pay Interconnection Costs
Cloud & Data Centers

Texas Grid Rules Push AI Data Centres To Pay Interconnection Costs

Texas regulators are moving AI data-centre projects into a stricter grid-planning process that adds financial security, interconnection charges and curtailment disclosure.

PJM Plan Makes AI Data Centres Prove Capacity For Firm Power
Cloud & Data Centers

PJM Plan Makes AI Data Centres Prove Capacity For Firm Power

Data Center Knowledge reported that PJM is proposing a FERC-filed framework that would make new AI data centres secure generating capacity or face curtailments during grid shortages.

PJM Backup-Generator Warnings Test Large-Load Grid Tool
Cloud & Data Centers

PJM Backup-Generator Warnings Test Large-Load Grid Tool

Data Center Knowledge reported that PJM issued emergency backup-generator warnings during a July heat wave but did not dispatch customer-owned generators, leaving total available large-load backup capacity undisclosed.

Finland Data Centre Growth Faces Grid And Heat-Reuse Tests
Cloud & Data Centers

Finland Data Centre Growth Faces Grid And Heat-Reuse Tests

Finland is attracting AI data centre projects because of low-carbon power, cool weather and land, Data Center Knowledge reported, but grid connections, permitting and waste-heat rules now determine how much capacity becomes operational.

Keep Reading

More Stories

Latest
Indosat AI Data Centre Plan Targets 1GW With Ooredoo, Nokia And NvidiaCloud & Data CentersAug 8, 2026Indosat AI Data Centre Plan Targets 1GW With Ooredoo, Nokia And NvidiaData Center Dynamics reported that Indosat, Ooredoo Group, Nokia and Nvidia launched Zankore by Indosat with a plan for up to 1GW of AI data centre capacity in Indonesia.Hugging Face Hack Pushes AI Agents Into Cybersecurity SpotlightAIAug 8, 2026Hugging Face Hack Pushes AI Agents Into Cybersecurity SpotlightCNBC reported that Black Hat cybersecurity leaders treated the Hugging Face AI-agent breach as a turning point for governing autonomous cyber models rather than a one-off failure.Alibaba Tests Revenue Sharing For Commercial Qwen AI UseAIAug 8, 2026Alibaba Tests Revenue Sharing For Commercial Qwen AI UseAI News reported that Alibaba plans revenue-sharing terms for some commercial users of its next Qwen open-weight AI model, following a licensing pattern already used by Moonshot for Kimi K3.Meta Ordered To Fund $567M New Mexico Youth Mental Health PlanCapital & PolicyAug 8, 2026Meta Ordered To Fund $567M New Mexico Youth Mental Health PlanArs Technica reported that a New Mexico judge ordered Meta to provide $567 million for treatment, screening, awareness and prevention after finding that its platforms contributed to a public nuisance.Harvey Funding Talks Could Lift Legal AI Startup To $15.5B ValuationAIAug 8, 2026Harvey Funding Talks Could Lift Legal AI Startup To $15.5B ValuationSiliconANGLE reported that Harvey AI is seeking at least $500 million in new funding that could value the legal AI startup at $15.5 billion after annualized revenue passed $350 million.Vietnam Shows Shopee-TikTok Shop Race Tightening In Southeast AsiaScience & TechAug 7, 2026Vietnam Shows Shopee-TikTok Shop Race Tightening In Southeast AsiaTech Collective SEA wrote that Shopee’s Vietnam share fell from 61% to 53% between May 2025 and April 2026 as TikTok Shop rose from 33% to 44%, showing how social commerce is reshaping regional ecommerce infrastructure.China Opens Security Review Of Palo Alto Networks ProductsCybersecurityAug 7, 2026China Opens Security Review Of Palo Alto Networks ProductsChina's cyberspace regulator opened a security review of Palo Alto Networks products, with no named product line, technical flaw or decision timetable disclosed.AI Pioneers Split Over Risk As Compute Buildout AcceleratesAIAug 7, 2026AI Pioneers Split Over Risk As Compute Buildout AcceleratesData Center Knowledge reported that Geoffrey Hinton, Fei-Fei Li and Andrew Ng disagreed at Ai4 over AI risk, jobs, openness and regulation, leaving infrastructure investors to plan capacity amid unsettled deployment rules.SpaceX Asks FCC To Wind Down $4.5bn Rural Broadband SupportTelco & ConnectivityAug 7, 2026SpaceX Asks FCC To Wind Down $4.5bn Rural Broadband SupportLight Reading reported that SpaceX urged the FCC to sunset High-Cost rural broadband subsidies, while rural telecom and electric-cooperative groups said LEO satellite coverage cannot replace terrestrial network support.OpenAI Expands Free ChatGPT Access In GPT-5.6 RolloutAIAug 7, 2026OpenAI Expands Free ChatGPT Access In GPT-5.6 RolloutBleepingComputer reported that OpenAI is rolling out GPT-5.6 Sol for paid ChatGPT users and GPT-5.6 Luna for Free and Go users, pairing unlimited free text chats with a new reasoning control and additional safeguards for users believed to be under 18.JLL Data Centre Report Shows Middle East Pipeline Pause As FLAPD GrowsCapital & PolicyAug 7, 2026JLL Data Centre Report Shows Middle East Pipeline Pause As FLAPD GrowsData Center Dynamics reported that JLL's EMEA Mid-Year Data Centre Report 2026 put FLAPD live capacity at 3.8GW, while the Middle East had 2.6GW in development paused and 13.8GW in planning.AWS Adds Persistent Runtime Instances For Production AI AgentsCloud & Data CentersAug 7, 2026AWS Adds Persistent Runtime Instances For Production AI AgentsAWS announced runtime instances for Amazon Bedrock AgentCore Runtime, adding managed infrastructure for multi-agent workflows, shared sessions lasting up to 14 days and GPU-supported production agent deployments.