SendTech Times
News
INFRASTRUCTURE CONSTRAINT:

Georgia Power Filings Show 3.2GW Grid Queue Before OpenAI Camellia Debut

Newsroom brief

Data Center Knowledge reviewed PSC filings that recorded a 3,200MW customer commitment and an anonymised 3,210MW project before OpenAI unveiled its $20 billion Project Camellia AI campus.

Verified against source materialEdited by SendTech Times Cloud & Infrastructure DeskSource: Data Center Knowledge
Georgia Power Filings Show 3.2GW Grid Queue Before OpenAI Camellia Debut
Image source: Data Center Knowledge

A 3.2GW AI campus was moving through Georgia utility planning before OpenAI gave the project a public name.

Data Center Knowledge reviewed Georgia Public Service Commission filings that recorded a 3,200MW customer commitment and an anonymized 3,210MW project before OpenAI unveiled the $20 billion Project Camellia campus.

The PSC record establishes the load sequence before the public launch, but it does not identify the confidential customer.

Project Camellia was announced as a 3.2GW AI campus, and the filing material shows how large-load planning can begin months before communities, developers, and other power users see the named project.

PSC Filings Recorded A 3,200MW Commitment

In a first-quarter 2026 large-load filing, Georgia Power recorded 3,200MW of new customer commitments for April 2026 and placed the fuller update in the next quarterly cycle.

OpenAI gave Project Camellia its public name three months after that April commitment appeared in the utility record.

An accompanying planning attachment identifies an anonymized project in technical review with an announced load of 3,210MW, an initial in-service date of Q2 2028, and a ramp to approximately 3.2GW by 2031.

The timeline broadly matches OpenAI's plan to energize the campus in phases beginning in 2028.

Neil Osnato, founder of Persistence Analytics Group, noted that the proposed 3.2GW draw was exceptional for utility planning.

His assessment treated the campus as a system-level load, not a conventional customer connection.

Georgia Power Raised Its Load Forecast

Georgia Power's January 2025 Integrated Resource Plan provides the planning context for early confidential evaluations.

The filing describes ongoing utility talks with large power users and incorporates both prospective and committed projects into long-term demand modeling.

The utility raised its load-growth forecast to 8,200MW through the winter of 2030-31, exceeding the 2023 IRP update by more than 2,200MW, and projected nearly 6,000MW of new demand by the winter of 2028-29.

The filing also proposed new generation resources and strategic transmission investments.

Whether Project Camellia contributed to that forecast cannot be determined from the public record.

A single 3.2GW campus illustrates the size of customer requests that can alter a utility's planning horizon before the project enters local economic-development debate and before local documents name the buyer.

OpenAI Deal Includes Demand Response Terms

Georgia Power's OpenAI agreement carried terms that were not visible in the PSC filings.

The utility put OpenAI under responsibility for full infrastructure and electric-service costs, financial assurances designed to protect existing customers and a 25-year agreement that includes up to 1,000MW of flexible demand response.

Under that arrangement, peak-demand periods can trigger reductions in power delivered to the campus.

The utility described the clause as one of the largest demand-response commitments attached to a single facility in the United States, making curtailment a formal part of the campus's grid connection rather than an afterthought.

Discovery responses in the PSC docket also illustrate how Georgia Power weighs large-load evidence.

Executed electric-service contracts carry more weight in forecasts than service requests, and one proposed data-center project left the queue after the developer stopped responding, lacked an operator, and no longer marketed the site as a data-center location.

Georgia Power's March 31 large-load materials reported committed large-load customers at 12.4GW, the economic-development pipeline at 76.2GW, and committed projects at 31, most of them data centres.

Those figures place Project Camellia within a much larger queue of AI and hyperscale power requests across the utility system.

Public Records Stop Before Customer Confirmation

County-level records add another boundary around the timeline.

The Effingham County Board of Commissioners had no Project Camellia references in agendas, meeting packets, or minutes before the announcement, and its open-records response found no maintained development, incentive, or correspondence files matching the request.

OpenAI has pledged to share Project Camellia water-use data, publish annual independent audits, and maintain community communication.

That transparency commitment begins after the named campus enters public view; the PSC timeline captures the earlier layer where large-load planning can appear under confidential customer labels.

The PSC filings therefore document the load size, stage, and energization schedule without naming the customer.

The PSC records do not identify OpenAI as the anonymous customer or establish when the 3.2GW load became commercially certain.

Share this article
inXf

Related articles

More
Meta Says Hyperion AI Campus Will Reach 5 GW In Louisiana
Cloud & Data Centers

Meta Says Hyperion AI Campus Will Reach 5 GW In Louisiana

Data Center Knowledge reported that Meta's Hyperion AI campus in Louisiana is being expanded to 5 GW and more than $50 billion of investment, with Entergy filings listing 1,500 MW of new solar and hybrid resources and customer-funded transmission for the expansion.

Amazon Grid Proposal Tests Who Pays For AI Data-Centre Lines
Cloud & Data Centers

Amazon Grid Proposal Tests Who Pays For AI Data-Centre Lines

Data Center Knowledge reported that Amazon asked Virginia regulators to let hyperscale data-centre customers voluntarily fund project-specific transmission upgrades, while Dominion argued the issue belongs in a separate proceeding.

FiberLight CEO Says AI Data Centres Now Follow Power Before Incentives
Cloud & Data Centers

FiberLight CEO Says AI Data Centres Now Follow Power Before Incentives

Capacity wrote that FiberLight CEO Bill Major sees power availability overtaking tax breaks and land costs in AI data centre site selection, with fibre connectivity still required for usable compute capacity.

Spain AI Campus Seeks 300 MW With On-Site Power Plan
Cloud & Data Centers

Spain AI Campus Seeks 300 MW With On-Site Power Plan

Data Center Knowledge reported that EdgeMode, BlackBerry AIF and Mora are seeking regional support for DC MALPICA, a proposed €3 billion ($3.4 billion), 300 MW AI campus whose power model remains partly undisclosed.

Texas Approves $13.8 Billion 765 kV Grid Plan For AI Data Centre Loads
Cloud & Data Centers

Texas Approves $13.8 Billion 765 kV Grid Plan For AI Data Centre Loads

AI data centre customers, final routes or ratepayer cost terms remain outside the public record.

Galaxy’s 74 MW McGregor AI Campus Commits To Private Texas Substation
Cloud & Data Centers

Galaxy’s 74 MW McGregor AI Campus Commits To Private Texas Substation

Galaxy Digital plans a 500-acre AI and high-performance computing campus in McGregor, Texas, with a 74 MW first phase and project commitments covering a private substation, utility assurances and water infrastructure.

Texas Grid Rules Push AI Data Centres To Pay Interconnection Costs
Cloud & Data Centers

Texas Grid Rules Push AI Data Centres To Pay Interconnection Costs

Texas regulators are moving AI data-centre projects into a stricter grid-planning process that adds financial security, interconnection charges and curtailment disclosure.

Ofgem Grid Fee Would Make Data-Centre Developers Prove Demand
Cloud & Data Centers

Ofgem Grid Fee Would Make Data-Centre Developers Prove Demand

Data Center Knowledge covered Ofgem’s proposed refundable Data Centre Commitment Fee, which would attach delivery milestones and a per-megawatt security requirement to large British data-centre grid applications.

Keep Reading

More Stories

Latest
Kepler Targets 2027 Production for HBM Replacement MemoryCloud & Data CentersOct 6, 2026Kepler Targets 2027 Production for HBM Replacement MemoryEE Times reports that Kepler Computing is preparing 3D ferroelectric memory for 2027 production, promising higher capacity and bandwidth per watt while limiting reliance on advanced-node lithography.Yokogawa Opens Singapore Hub For Industrial Cyber ResilienceCapital & PolicyOct 6, 2026Yokogawa Opens Singapore Hub For Industrial Cyber ResilienceYokogawa Engineering Asia has launched a Singapore center focused on OT cyber resilience, training, response planning and recovery coordination for Southeast Asia, Oceania and Taiwan.ClickFix Attack Uses Browser Cache To Hide Malware PayloadCybersecurityOct 6, 2026ClickFix Attack Uses Browser Cache To Hide Malware PayloadMicrosoft Threat Intelligence traced a ClickFix cache-smuggling method that preloads malware into browser caches, then uses file size checks and a pasted Run command to launch later credential-theft stages.VOA Tests Six-Month Startup Buildout Before Funding DecisionsFintech & Digital PaymentsOct 6, 2026VOA Tests Six-Month Startup Buildout Before Funding DecisionsTechCabal’s interview with VOA Venture Partners founder Victoria Olayide Adesanya describes a six-month build programme that lets the firm work inside African financial-infrastructure startups before deciding whether to invest.Bitcoin Holds $86,000 As Dollar Index Hits 18-Month HighCrypto/Web3Oct 6, 2026Bitcoin Holds $86,000 As Dollar Index Hits 18-Month HighCoinDesk reported that bitcoin stayed near $86,000 while the U.S. Dollar Index reached about 102.5, with U.S. rate expectations and European political risks strengthening the dollar backdrop.Google Freezes OSS Bug Bounty Reports After AI Submission FloodCybersecurityOct 6, 2026Google Freezes OSS Bug Bounty Reports After AI Submission FloodGoogle has stopped accepting new product vulnerability reports in its OSS VRP after invalid automated submissions swamped reviewers, while older reports and some Cloud VRP routes remain open.Fleuret AI Raises €4M For Continuous AI Pentesting PlatformCybersecurityOct 6, 2026Fleuret AI Raises €4M For Continuous AI Pentesting PlatformTech.eu reported that French startup Fleuret AI raised €4 million in pre-seed funding to develop an agentic-AI platform that turns penetration testing into a continuous security process.GFT Analysis Says AI Documentation Can Cut Maintenance Work 30%Fintech & Digital PaymentsOct 6, 2026GFT Analysis Says AI Documentation Can Cut Maintenance Work 30%A GFT Technologies analysis says AI-linked software documentation can cut maintenance effort and speed developer onboarding when knowledge assets stay synchronized with code changes.Schneider Electric Lines Up $22.6 Billion PTC DealAIOct 5, 2026Schneider Electric Lines Up $22.6 Billion PTC DealSchneider Electric plans to buy PTC in a cash transaction valuing the US engineering software provider’s equity at about $22.6 billion, adding product-lifecycle software to its industrial AI push.Aggarwal Pledges Ola Electric Stake To Fund ₹1,000 Cr Rights IssueCapital & PolicyOct 5, 2026Aggarwal Pledges Ola Electric Stake To Fund ₹1,000 Cr Rights IssueOla Electric founder Bhavish Aggarwal pledged 20 Cr shares to finance his participation in a rights issue that forms part of a larger ₹1,500 Cr fundraising plan.Natrona Schools AI Review Puts Student Privacy Ahead Of Classroom Tool UseAIOct 5, 2026Natrona Schools AI Review Puts Student Privacy Ahead Of Classroom Tool UseNatrona County trustees questioned whether teacher AI tools expose student data, even as existing district rules already ban unauthorized generative AI use by students.AMD Prices 256-Core EPYC 9996 At $14,904 For Server BuyersChips & SemiconductorsOct 5, 2026AMD Prices 256-Core EPYC 9996 At $14,904 For Server BuyersTechRadar reports that AMD’s 6th Gen EPYC 9006 “Venice” lineup includes a 256-core EPYC 9996 with 512 threads, 1GB of L3 cache, a 600W default power rating and a $14,904 list price for 1,000-unit orders.