Power Constraints Push Data Centre Growth Into Secondary Markets
Data Center Knowledge reported that DCByte rankings now put power delivery ahead of demand in data centre site selection, with constrained hubs such as Ashburn and Tokyo losing some growth momentum to markets including Johor, Pittsburgh and Zaragoza.

Power access is becoming the first test for turning data centre demand into usable capacity.
Data Center Knowledge reported on August 5 that DCByte's latest market rankings show developers giving more weight to places where grid links, planning rules and construction conditions can support actual delivery.
The pressure sits in the distance between sales demand and energization.
DCByte's index assigns 40% of its score to contracted capacity, 35% to capacity that is committed or being built, and 25% to live inventory, so a deep market can still rank poorly for future growth if electricity cannot reach projects on time.
Mature Hubs Keep Customers But Face Slower Delivery
Ashburn, Virginia, remains the Americas leader and the core of the largest global data centre market.
The DCByte figures list 5.6 GW already operating there and 15 GW more in the first-quarter pipeline, while grid-link waits can run five to seven years.
That lag changes how operators value land near cloud regions and network routes.
A parcel has limited practical value when transmission access, substations or interconnection work cannot match the build schedule.
Tokyo's power-connection wait can stretch to roughly 10 years, and constrained-core labels now apply to Dublin and Amsterdam because regulation, power and local resistance limit conversion of demand into capacity.
Growth Rankings Move Toward Easier Build Paths
DCByte's future-growth tables favor markets where developers see fewer delivery barriers.
The DCByte future-growth rankings cited by Data Center Knowledge put Pittsburgh, Charlotte and Austin first in the Americas; Kuala Lumpur, Bangkok and Jakarta first in APAC; and Zaragoza, Milan and Berlin first in EMEA.
Johor shows the pace of the shift.
Capacity in the Malaysian market was below 10 MW five years earlier and reached about 1 GW over a four-year span, changing its role from overflow for Singapore into the region's fastest-emerging growth location.
Grid Access Is Now A Permitting And Supply-Chain Question
Developers have to measure more than headline electricity generation.
Usable capacity depends on transmission routes, available substations, queue position and staged power-up plans that fit a commercial timetable.
The same assessment reaches into equipment and local infrastructure.
Transformers, switchgear, gas turbines, fiber routes, water access, construction labor and support for liquid-cooled AI racks near or above 100 kW all affect whether a site can open as planned.
Local approval has become part of the power equation as governments review resource use, incentives, environmental impact and durable employment.
The next site-selection advantage belongs to regions that can align power procurement, permits, construction and community approval before AI infrastructure demand outruns the delivery path.