INFRASTRUCTURE CONSTRAINT:

EdgeConneX Plans 500MW+ Malaysia AI Data Centre Capacity

Newsroom brief

Tech Wire Asia published sponsored material saying EdgeConneX is building more than 500MW of AI-ready capacity across Cyberjaya and Johor, with rack designs from 20kW to 600kW+ and closed-loop cooling. Signed tenants, contracted capacity and customer deployment dates remain outside the sponsored account.

Verified against source materialEdited by SendTech Times Cloud & Infrastructure DeskSource: Tech Wire Asia
EdgeConneX Plans 500MW+ Malaysia AI Data Centre Capacity

Sponsored Tech Wire Asia material outlined plans for more than 500MW of AI-ready data centre capacity across EdgeConneX campuses in Cyberjaya and Johor, with rack designs ranging from 20kW to 600kW+.

It portrayed the Malaysian sites as being built for GPU-intensive workloads, liquid-cooling requirements and modular power blocks.

The same sponsored account also detailed a closed-loop cooling design for the two campuses.

Cyberjaya And Johor Add 500MW+ Of AI Data Centre Capacity

The sponsored material outlined two hyperscale campuses in Malaysia, with Cyberjaya and Johor intended for AI training, inference and hybrid cloud workloads.

The facilities are presented as supporting racks that can begin at 20kW to 200kW and scale to 600kW+ as GPU deployments expand.

At Cyberjaya, a 275kV substation serves as the anchor, and the material characterises it as the first of its kind in the greater Kuala Lumpur region.

The sponsored account indicates the substation would support phase one in Q1 2027, while data halls can be served by one or multiple 12MW power blocks.

In the same account, older data centres are described as commonly handling 10-15kW per rack, while modern AI training clusters need 50-100kW.

It adds that next-generation GPU architectures are moving towards 200-600kW, and that EdgeConneX designed higher ceilings, reinforced floors, electrical distribution and mechanical systems for 20-30-year facility lifespans.

Johor contributes another 180MW of planned capacity, with phase one also slated for 2027.

The sponsored material positions the site for customers that need proximity to Singapore while using Malaysia's cost structure and regulatory environment.

Cooling Design Claims Daily Water Savings

Both facilities are described as using closed-loop, non-evaporative heat-rejection technology rather than water-intensive evaporative cooling.

The material lists estimated daily water savings of 9 million litres at Cyberjaya and 7.6 million litres at Johor, or 16.6 million litres across both sites.

EdgeConneX also cites a water-neutrality target across its portfolio by 2030.

Once operations begin, the sponsored account schedules the Malaysian sites for UL 2799 certification within 18-24 months, following zero-waste-to-landfill certification at facilities including Jakarta.

Those environmental and performance claims remain company-linked.

The public account does not provide measured power-usage effectiveness for the Malaysian campuses, third-party operating data or named hyperscale customers for the first phases.

NVIDIA DGX Certification Frames The GPU Workload

The sponsored material presents EdgeConneX as an NVIDIA DGX certified partner and states that the infrastructure meets NVIDIA reference standards for power delivery, cooling compatibility and network architecture.

Specific DGX customers, cluster orders and server vendors for the Malaysian sites remain outside the public account.

The account lists 90+ data centres globally and gigawatt-scale operations across North America, Europe and Asia-Pacific.

Across EdgeConneX's Asia-Pacific facilities, local teams operate with regional and global support where needed, the sponsored account notes.

It also lists Malaysia workforce and education programmes planned for the second half of 2026.

Project budgets and hiring targets for those programmes remain outside the account.

The remaining public gaps are signed tenants, contracted capacity, facility-level PUE results, construction costs and customer deployment dates for the Cyberjaya and Johor campuses.

Share this article
inXf

Related articles

More
Malaysia AI Data Centres Put Fibre And Power Supply On Critical Path
Cloud & Data Centers

Malaysia AI Data Centres Put Fibre And Power Supply On Critical Path

Panduit told reporters in Kuala Lumpur that Malaysia’s AI data-centre expansion depends on fibre, rack power and compliant installation as much as headline GPU capacity.

Anthropic Signs $19 Billion TeraWulf Lease Without Naming Hawesville Chips
Cloud & Data Centers

Anthropic Signs $19 Billion TeraWulf Lease Without Naming Hawesville Chips

Anthropic agreed to a $19 billion, 20-year TeraWulf data-centre lease for a 401MW Kentucky campus. TeraWulf disclosed the site, cooling design and investment range, while chip selection and the first capacity tranche remain outside the public record.

Vertiv Opens Johor AI Cooling Plant As Data Centre Approvals Tighten
Cloud & Data Centers

Vertiv Opens Johor AI Cooling Plant As Data Centre Approvals Tighten

Vertiv says it has opened its first Southeast Asian manufacturing base in Johor to make AI data-centre power and cooling equipment. Vertiv says the plant is shipping from phase one and targets full technical capacity in 2027, while Malaysian agencies say Johor is weighing data-centre power and water demand more selectively.

Delta GoCool-150 Shows The Cooling Cost Of A 150kW AI Rack
Cloud & Data Centers

Delta GoCool-150 Shows The Cooling Cost Of A 150kW AI Rack

ServeTheHome reported that Delta displayed a GoCool-150 liquid-to-air cooling unit for Nvidia Vera Rubin NVL72 racks, with 150kW heat removal, 225 litres per minute of coolant flow and a 32-fan rear array.

Galaxy’s 74 MW McGregor AI Campus Commits To Private Texas Substation
Cloud & Data Centers

Galaxy’s 74 MW McGregor AI Campus Commits To Private Texas Substation

Galaxy Digital plans a 500-acre AI and high-performance computing campus in McGregor, Texas, with a 74 MW first phase and project commitments covering a private substation, utility assurances and water infrastructure.

Sunrun Plans Home AI Compute Pilot Without Naming Enterprise Buyers
Cloud & Data Centers

Sunrun Plans Home AI Compute Pilot Without Naming Enterprise Buyers

A distributed AI compute pilot would place inference nodes in homes with solar and battery systems, using more than 1.1 million customers as a possible deployment base while enterprise buyers, node counts and hosting economics remain public gaps.

Singapore Bill Puts Data Centres Under $1m Or 10% Turnover Penalty
Cloud & Data Centers

Singapore Bill Puts Data Centres Under $1m Or 10% Turnover Penalty

Asian Business Review reported that Singapore's Digital Infrastructure bill would license major data centre and cloud infrastructure providers after a 2023 cooling failure disrupted more than 2.5 million payment and ATM transactions.

Google India Data Centre Dispute Brings Texas Water Lessons To AI Build-Out
Cloud & Data Centers

Google India Data Centre Dispute Brings Texas Water Lessons To AI Build-Out

Capacity Media linked opposition to Google’s Andhra Pradesh data centre plans with Texas disputes over water, approvals and community trust around hyperscale infrastructure.

Keep Reading

More Stories

Latest
Ethereum Testnet Update Targets 200 Million-Gas BlocksCrypto/Web3Oct 6, 2026Ethereum Testnet Update Targets 200 Million-Gas BlocksEthereum developers released Prysm 7.2.1 so the Sepolia trial of Glamsterdam can test 200 million-gas blocks, more than three times the prior 60 million setting, before any main-network change.Kepler Targets 2027 Production for HBM Replacement MemoryCloud & Data CentersOct 6, 2026Kepler Targets 2027 Production for HBM Replacement MemoryEE Times reports that Kepler Computing is preparing 3D ferroelectric memory for 2027 production, promising higher capacity and bandwidth per watt while limiting reliance on advanced-node lithography.Yokogawa Opens Singapore Hub For Industrial Cyber ResilienceCapital & PolicyOct 6, 2026Yokogawa Opens Singapore Hub For Industrial Cyber ResilienceYokogawa Engineering Asia has launched a Singapore center focused on OT cyber resilience, training, response planning and recovery coordination for Southeast Asia, Oceania and Taiwan.ClickFix Attack Uses Browser Cache To Hide Malware PayloadCybersecurityOct 6, 2026ClickFix Attack Uses Browser Cache To Hide Malware PayloadMicrosoft Threat Intelligence traced a ClickFix cache-smuggling method that preloads malware into browser caches, then uses file size checks and a pasted Run command to launch later credential-theft stages.VOA Tests Six-Month Startup Buildout Before Funding DecisionsFintech & Digital PaymentsOct 6, 2026VOA Tests Six-Month Startup Buildout Before Funding DecisionsTechCabal’s interview with VOA Venture Partners founder Victoria Olayide Adesanya describes a six-month build programme that lets the firm work inside African financial-infrastructure startups before deciding whether to invest.Bitcoin Holds $86,000 As Dollar Index Hits 18-Month HighCrypto/Web3Oct 6, 2026Bitcoin Holds $86,000 As Dollar Index Hits 18-Month HighCoinDesk reported that bitcoin stayed near $86,000 while the U.S. Dollar Index reached about 102.5, with U.S. rate expectations and European political risks strengthening the dollar backdrop.Google Freezes OSS Bug Bounty Reports After AI Submission FloodCybersecurityOct 6, 2026Google Freezes OSS Bug Bounty Reports After AI Submission FloodGoogle has stopped accepting new product vulnerability reports in its OSS VRP after invalid automated submissions swamped reviewers, while older reports and some Cloud VRP routes remain open.Fleuret AI Raises €4M For Continuous AI Pentesting PlatformCybersecurityOct 6, 2026Fleuret AI Raises €4M For Continuous AI Pentesting PlatformTech.eu reported that French startup Fleuret AI raised €4 million in pre-seed funding to develop an agentic-AI platform that turns penetration testing into a continuous security process.GFT Analysis Says AI Documentation Can Cut Maintenance Work 30%Fintech & Digital PaymentsOct 6, 2026GFT Analysis Says AI Documentation Can Cut Maintenance Work 30%A GFT Technologies analysis says AI-linked software documentation can cut maintenance effort and speed developer onboarding when knowledge assets stay synchronized with code changes.Schneider Electric Lines Up $22.6 Billion PTC DealAIOct 5, 2026Schneider Electric Lines Up $22.6 Billion PTC DealSchneider Electric plans to buy PTC in a cash transaction valuing the US engineering software provider’s equity at about $22.6 billion, adding product-lifecycle software to its industrial AI push.Aggarwal Pledges Ola Electric Stake To Fund ₹1,000 Cr Rights IssueCapital & PolicyOct 5, 2026Aggarwal Pledges Ola Electric Stake To Fund ₹1,000 Cr Rights IssueOla Electric founder Bhavish Aggarwal pledged 20 Cr shares to finance his participation in a rights issue that forms part of a larger ₹1,500 Cr fundraising plan.Natrona Schools AI Review Puts Student Privacy Ahead Of Classroom Tool UseAIOct 5, 2026Natrona Schools AI Review Puts Student Privacy Ahead Of Classroom Tool UseNatrona County trustees questioned whether teacher AI tools expose student data, even as existing district rules already ban unauthorized generative AI use by students.