Google and Energy Dome plan a 23MW/200MWh long-duration storage plant in Rhode, Ireland, with land, planning consent, grid connection and an EirGrid capacity contract already secured.

Verified against source materialEdited by SendTech Times Cloud & Infrastructure DeskSource: Data Center Dynamics
Google And Energy Dome Put A 23MW Storage Project Behind Ireland Data Center Demand
Image source: Data Center Dynamics / Energy Dome

Google Links Storage To Ireland's Data Center Grid Constraint

Google and Energy Dome are developing a 23MW/200MWh long-duration energy storage project in Rhode, Ireland, putting a data-center power constraint into a specific grid asset rather than a broad clean-energy pledge.

The project is expected to come online in 2028.

The storage plant is part of a long-term agreement signed last year to deploy Energy Dome's technology at scale and support Google's low-carbon efforts.

Energy Dome will develop, own and operate the plant, with Lumcloon Energy involved as a renewable developer.

Rhode Site Already Has Grid And Planning Milestones

The project is located at the site of a former peat-fired power station in County Offaly, close to the town of Rhode.

The companies described the location as a crucial node of the electrical grid, with high-voltage lines serving the Greater Dublin area, where data center facilities are concentrated.

The project has already secured land, planning consent and a grid connection.

It has also received a ten-year capacity contract from EirGrid, Ireland's state-owned transmission system operator.

Energy Dome also plans a second 200MWh unit at the same site.

Storage Becomes Part Of Google's Infrastructure Burden

Ireland was selected after long-duration storage became a key part of the country's energy system planning, alongside a goal of reaching 80 percent renewable energy generation by 2030.

For Google, that turns storage into part of the operating infrastructure behind cloud and AI demand, not a separate sustainability footnote.

The project also shows how data-center expansion increasingly depends on assets outside the server hall: grid nodes, capacity contracts, storage duration and local planning approvals.

Google Ireland's head Vanessa Hartley said the project is a step in the partnership with Energy Dome and will help scale the company's long-duration storage technology.

Capacity Delivery Is Still Ahead

Energy Dome founder and CEO Claudio Spadacini said the project will demonstrate CO2 Battery technology in Ireland while supporting a clean energy future.

The company is still moving from secured site conditions and grid approvals toward actual delivery of the storage plant.

The unresolved operating burden is the 2028 delivery date: Google and Energy Dome have land, planning consent, grid connection and an EirGrid capacity contract, but the 23MW/200MWh plant still has to enter service before it can relieve pressure near Dublin's data center cluster.

Share this article
inXf

Related articles

More
Google Says AI Demand Is Outrunning Grid Decarbonisation
Cloud & Data Centers

Google Says AI Demand Is Outrunning Grid Decarbonisation

Google said its electricity demand climbed 37% in 2025 and has grown more than 250% since 2019 as AI and cloud infrastructure expanded. The company also cited 1 GW of demand-response capacity and more than 12 GW of new clean generation deals, while the public record still lacks what share of its total computing load can shift during grid stress.

US Bill Would Make Large Data Centers Pay For Grid Upgrades
Cloud & Data Centers

US Bill Would Make Large Data Centers Pay For Grid Upgrades

The Ratepayer Protection Act would push US data centers of 100MW or more to cover generation, transmission and connection costs, moving AI power demand into a federal ratepayer fight.

Phoenix Group Takes UAE AI Data-Center Capital Into Europe With DC Max Deal
Cloud & Data Centers

Phoenix Group Takes UAE AI Data-Center Capital Into Europe With DC Max Deal

Abu Dhabi-based Phoenix Group is partnering with France’s DC Max on an 18MW AI-ready data center in Lyon, using the project as the first step in a platform targeting more than 1GW of AI and HPC capacity across Europe and the GCC. The deal centers on land, permits, grid access and the speed required to meet AI compute demand.

Foreign Grid Equipment Order Adds Data-Center Power Checkpoint
Cloud & Data Centers

Foreign Grid Equipment Order Adds Data-Center Power Checkpoint

Data Center Knowledge reported that a US executive order on foreign bulk-power equipment could add procurement and lifecycle reviews to data-center power projects already facing long lead times.

Texas Grid Audit Freezes Data Centre Queue As AI Demand Builds
Cloud & Data Centers

Texas Grid Audit Freezes Data Centre Queue As AI Demand Builds

Capacity reported that Texas has paused new data centre approvals while ERCOT and PUCT audit Batch Zero projects seeking grid access, a group of 250 to 300 projects representing about 200GW of future demand.

GM Sodium-Ion Storage Push Turns AI Data Center Power Into A Battery Market Test
Cloud & Data Centers

GM Sodium-Ion Storage Push Turns AI Data Center Power Into A Battery Market Test

General Motors is expanding into grid-scale energy storage through Peak Energy, LG Energy Solution and Redwood Materials, making AI data center demand a battery commercialization test.

PJM Plan Makes AI Data Centres Bring Power Or Accept Curtailment
Cloud & Data Centers

PJM Plan Makes AI Data Centres Bring Power Or Accept Curtailment

Data Center Knowledge reported that PJM's proposed IRAS framework would separate grid connection from firm service for new AI-scale loads, pushing data centre developers to bring capacity, contract bilaterally or accept curtailment during shortages.

US Energy Chief Tells Data Centre Builders To Answer Power Critics
Cloud & Data Centers

US Energy Chief Tells Data Centre Builders To Answer Power Critics

US Energy Secretary Chris Wright used an AWS Summit appearance to tell data centre supporters to engage critics over electricity costs and local opposition as AI construction raises power and permitting pressure.

Keep Reading

More Stories

Latest
Kepler Targets 2027 Production for HBM Replacement MemoryCloud & Data CentersOct 6, 2026Kepler Targets 2027 Production for HBM Replacement MemoryEE Times reports that Kepler Computing is preparing 3D ferroelectric memory for 2027 production, promising higher capacity and bandwidth per watt while limiting reliance on advanced-node lithography.Yokogawa Opens Singapore Hub For Industrial Cyber ResilienceCapital & PolicyOct 6, 2026Yokogawa Opens Singapore Hub For Industrial Cyber ResilienceYokogawa Engineering Asia has launched a Singapore center focused on OT cyber resilience, training, response planning and recovery coordination for Southeast Asia, Oceania and Taiwan.ClickFix Attack Uses Browser Cache To Hide Malware PayloadCybersecurityOct 6, 2026ClickFix Attack Uses Browser Cache To Hide Malware PayloadMicrosoft Threat Intelligence traced a ClickFix cache-smuggling method that preloads malware into browser caches, then uses file size checks and a pasted Run command to launch later credential-theft stages.VOA Tests Six-Month Startup Buildout Before Funding DecisionsFintech & Digital PaymentsOct 6, 2026VOA Tests Six-Month Startup Buildout Before Funding DecisionsTechCabal’s interview with VOA Venture Partners founder Victoria Olayide Adesanya describes a six-month build programme that lets the firm work inside African financial-infrastructure startups before deciding whether to invest.Bitcoin Holds $86,000 As Dollar Index Hits 18-Month HighCrypto/Web3Oct 6, 2026Bitcoin Holds $86,000 As Dollar Index Hits 18-Month HighCoinDesk reported that bitcoin stayed near $86,000 while the U.S. Dollar Index reached about 102.5, with U.S. rate expectations and European political risks strengthening the dollar backdrop.Google Freezes OSS Bug Bounty Reports After AI Submission FloodCybersecurityOct 6, 2026Google Freezes OSS Bug Bounty Reports After AI Submission FloodGoogle has stopped accepting new product vulnerability reports in its OSS VRP after invalid automated submissions swamped reviewers, while older reports and some Cloud VRP routes remain open.Fleuret AI Raises €4M For Continuous AI Pentesting PlatformCybersecurityOct 6, 2026Fleuret AI Raises €4M For Continuous AI Pentesting PlatformTech.eu reported that French startup Fleuret AI raised €4 million in pre-seed funding to develop an agentic-AI platform that turns penetration testing into a continuous security process.GFT Analysis Says AI Documentation Can Cut Maintenance Work 30%Fintech & Digital PaymentsOct 6, 2026GFT Analysis Says AI Documentation Can Cut Maintenance Work 30%A GFT Technologies analysis says AI-linked software documentation can cut maintenance effort and speed developer onboarding when knowledge assets stay synchronized with code changes.Schneider Electric Lines Up $22.6 Billion PTC DealAIOct 5, 2026Schneider Electric Lines Up $22.6 Billion PTC DealSchneider Electric plans to buy PTC in a cash transaction valuing the US engineering software provider’s equity at about $22.6 billion, adding product-lifecycle software to its industrial AI push.Aggarwal Pledges Ola Electric Stake To Fund ₹1,000 Cr Rights IssueCapital & PolicyOct 5, 2026Aggarwal Pledges Ola Electric Stake To Fund ₹1,000 Cr Rights IssueOla Electric founder Bhavish Aggarwal pledged 20 Cr shares to finance his participation in a rights issue that forms part of a larger ₹1,500 Cr fundraising plan.Natrona Schools AI Review Puts Student Privacy Ahead Of Classroom Tool UseAIOct 5, 2026Natrona Schools AI Review Puts Student Privacy Ahead Of Classroom Tool UseNatrona County trustees questioned whether teacher AI tools expose student data, even as existing district rules already ban unauthorized generative AI use by students.AMD Prices 256-Core EPYC 9996 At $14,904 For Server BuyersChips & SemiconductorsOct 5, 2026AMD Prices 256-Core EPYC 9996 At $14,904 For Server BuyersTechRadar reports that AMD’s 6th Gen EPYC 9006 “Venice” lineup includes a 256-core EPYC 9996 with 512 threads, 1GB of L3 cache, a 600W default power rating and a $14,904 list price for 1,000-unit orders.